Name of the Contract | Client | Work | Nos of Structure | Rs. (Crore) | % Work Completed |
|---|---|---|---|---|---|
Four Laning of Punjab/Haryana Border-Jind Section of NH-71 from Km. 238.695 to Km. 307.00 under NHDP Phase-IVB in the State of Haryana on EPC mode | M/s Dineshchandra | Bridge Work | 1 No- ROB. 4 Nos-Flyover 4 Nos-LVUP | 20 Crs | 100% |
Widening and Rehabilitation of Existing Patiala Bypass Road Km 50+000 to 69+250 on NH | M/s Dineshchandra | Bridge Work | 2 Nos-Flyover 4 Nos-LVUP 6 Nos PUP 10 Box Cul | 10Crs | 100% |
Construction of Two Lane ROB in lieu of Level crossing No 11 at IR chainage 14/2- 3 between Khori and Pali Station on Rewari- Phulera Section of Jaipur Division of NWR | Maan-Rana (JV) | Road Work& ROB& RE wall | 1 No- ROB 14 Span , RE Wall and Road Work | 22.50 Crs | 100% |
Construction of Six-Lane access controlled highway (NH-152D) starting From Ismailabad on NH-152 to Junction with Karnal – Pehowe Road (SH-9) near hand(Km. 00+000 to Km. 23+000 Length 23 Km.) under Bharatmala Pariyojana in the State of Haryana on EPC mode. | Celgal Pvt Ltd-Shiv Buildindia Pvt Ltd (JV) | Bridge Work | 3 Nos- LVUP 4 Nos-SVUP 2 Nos -MJB 10 Nos- Box. | 05 Crs | 100% |
Construction of Six-Lane access-controlled highway (NH-152D) starting from Junction with Jind-Safidon Road (SH-14) near Kheri village to Junction with NH-352 (Jind-Gohana Section) near Julana (Km. 80+000 to Km.108+000 Length 28 Km.) under Bharatmala Pariyojana in the State of Haryana on EPC mode. | Shiv Buildindia Pvt Ltd | Bridge Work | 1No-ROB 2 Nos- LVUP 2 Nos- | 20 Crs | 100% |
Construction of Six-Lane access-controlled highway (NH-152D) starting from Junction with Jind-Safidon Road (SH-14) near Kheri village to Junction with NH-352 (Jind-Gohana Section) near Julana (Km. 132+000 to Km.160+000 Length 28 Km.) under Bharatmala Pariyojana in the State of HR | Gawar Construction LTD | Bridge Work | 1No-ROB 3Nos Flyover 5 Nos- LVUP 5 Nos-SVUP 4 Nos -MJB | 15 Crs | 100% |
Four Laining of Dewas Ujjain Section of Old SH18 from Design Ch. 0+000 to 19+733, Construction of Four Lane Ujjain Bypass from Design Ch. 19+733 to Ch. 26+900 (Part-I) and Construction of Four Lane Dewas Bypass from Design Ch. 0+000 to Ch. 14+520 (Part-II) having total Design Length 41.42 KM in the state of MPon HAM Mode. | Dhariwal Buildtech Limited | Bridge Work | 1No- ROB 9 Nos Flyover | 40 Crs | 100% |
Construction of Four Laining of Rajauli to Bakhtiyarpur Section (Package-III) NH-20 State of BR | Gawar Construction LTD | Bridge Work | 2.5 KM Flyover & MNB | 45 Crs | 100% |
Construction of Six Laining of Flyover Raha, Demow, Borghat and ROB NH-36 and NH-37 State of Assam EPC Mode | Dhariwal Buildtech Limited | Bridge Work | Road Work and ROB | 70 Crs | 100% |
Development of six lane access control greenfield highway of Delhi-Saharanpur- Dehradun economic corridor under Bharatmala Pariyojana from Design Chainage 0+000(Akshardham NH-9 (old NH-24) to Design Chainage 14+750 (Delhi/UP border) in the state of Delhi (Package-1) on EPC mode. | Gawar Construction LTD | Bridge Work | Elevated Structure | 30 Crs | 100% |
Project: - Two/Four Laning of Brt Tiger Reserve Boundary to Bangalore Section Of NH-209 (Existing Chainage from Km. 287+520 To Km 461+550) in the State of Karnataka on Hybrid Annuity Mode Under NHDP Phase-IV. | Gawar Construction LTD | All Civil Work | Road Work and Bridges | 110 Crs | 100% |
Four laning of Bhiwani – Hansi Road section of NH – 148B (Design length 42.934 Km) under Bharatmala Pariyojana in the State of Haryana on Hybrid Annuity Mode (HAM) | Gawar Construction LTD | All Civil Work | Road Work and Bridges | 75 Crs | Work In Progress |
Four Laning of NH-119 from Behsuma at km 39.250 (Ex. Km 39+240 to Bijnor at km 78.810 (Ex. Km 86+590) (Design Length=39.560Km) in the state of Uttar Pradesh on Hybrid Annuity Mode | Gawar Construction LTD | Bridge Work | MJB, MNB and Underpasses | 20 Crs | Work In Progress |